Town of Hempstead
Completed Projects
Levittown
Start date: September 2021
Posted date: September 8, 2021
The route will cover approximately 0.25 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Blue Spruce Road between Newbridge Road and Oaktree Lane
Division Avenue between Schoolhouse Road and Church Road
Floral Park, Elmont and Franklin Square
Start date: January 2021
Posted date: January 20, 2021
The route will cover approximately 4.64 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Northern Zone
Childs Avenue between Atlantic Avenue and Floral Boulevard
Floral Boulevard between Daisy Avenue and Childs Avenue
Daisy Avenue between Floral Boulevard and Calla Avenue
Zinnia Street between Calla Avenue and Plainfield Avenue
Plainfield Avenue between Clarence Street and just north of Hempstead Turnpike (NY-24)
Chelsea Street between Plainfield Avenue and Carnegie Avenue
Elmont Road between the intersection with Plainfield Avenue and Hempstead Turnpike (NY-24)
Southern Zone
Hempstead Turnpike (NY-24) between Sterling Road and just east of Holland Avenue
Rear property between Sterling Road and Warwick Road between Hempstead Turnpike (NY-24) and Hathaway Avenue
Hathaway Avenue between Sussex Road and Warwick Road
Len Road between Hathaway Avenue and to just east of intersection of Ludlam Avenue
Frederick Avenue between Chelsea Street and Makofske Avenue
Makofske Avenue between Frederick Avenue and Hempstead Turnpike (NY-24)
Hempstead Turnpike (NY-24) between Makofske Avenue and Grand Street
Leher Avenue just south of Hempstead Turnpike (NY-24)
Covert Avenue between Hempstead Turnpike (NY-24) and Court Street
Clinton Street
LIPA Right of Way between Clinton Street and Grand Street
Oceanside
Start Date: February 2022
Posted Date: February 18, 2022
The route will cover approximately .7 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Long Beach Road between Foxhurst Road and Howard Place
Foxhurst Road between Long Beach Road and Dalto Court
Village of Garden City
Start Date: March 2022
Posted Date: March 14, 2022
The route will cover approximately .85 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Stratford Avenue between New Hyde Park Road and Hayes Street
New Hyde Park Road between Stratford Avenue and Manor Road
Stewart Avenue between Fernwood Terrace N and New Hyde Park Road
Rear property of homes 98-126, 99-121 and 213 on Meadbrook Road between Stratford Avenue and Stewart Avenue
Rear Property of homes 74, 78, 82, and 84 on Roxbury Road between Stewart Avenue and North Avenue
Wantagh and Seaford
Posted Date: October 26, 2022
The route will cover approximately .98 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Park Avenue between Merikoke Avenue and Beech Street
Wantagh Avenue between Lufberry Avenue and Demott Avenue
Washington Avenue between Boston Avenue and Clark Street
Baldwin
Start Date: Early September 2022
Posted Date: August 29, 2022
The route will cover approximately 1.08 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Central Avenue between Cottage Place and Sunrise Highway
Smith Street between Grand Avenue and Marion Place
Grand Avenue between Miller Place and Stanton Avenue
Hicksville (Town of Oyster Bay) East Meadow and Salisbury (Town of Hempstead)
Start Date: January 2022
Posted Date: December 17, 2021
The route will cover approximately 1.31 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
West Old Country Road between Tec Street and Mead Avenue
Stewart Avenue between Choir Lane S and Levittown Parkway