Town of Islip
Completed Projects
Sayville
Start Date: January 2022
Posted Date: December 16, 2021
The route will cover approximately 2.88 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Lincoln Avenue between Partington Street and Hiddink Street
Manton Street between Greeley Avenue and Lincoln Avenue
Greeley Avenue between Manton Street and Easy Street
Easy Street between Roosevelt Avenue and Greeley Avenue
Lakeland Avenue between Tariff Street and Henry Street
Railroad Avenue between Henry Street and Montauk Highway
Henry Street between Railroad Avenue and Lincoln Avenue
Overton Street between Lincoln Avenue and Montauk Highway
Montauk Highway between Overton Street and Millpond Road
Hiddink Street between Lincoln Avenue and Montauk Highway
Brentwood
Start Date: March 2022
Posted Date: March 1, 2022
The route will cover approximately .86 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Washington Avenue between Perry Street and Hale Street
Washington Avenue East on Clarke Street
Washington Avenue West on Heyward Street
Washington Avenue West on Walton Street
McWhorter Street between Reese Avenue and Washington Avenue
Reese Avenue between McWhorter Street and Suffolk Avenue
Suffolk Avenue between Monroe Avenue and Washington Avenue
Fourth Street between Suffolk Avenue and Second Avenue
1st Avenue between Fourth Street Brentwood Road
Hamlet of Bay Shore
Start Date: March 2022
Posted Date: March 14, 2022
The route will cover approximately 1.31 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
E Main Street/Montauk Highway between intersection at 4th Avenue and Maple Avenue and S Saxon Avenue
S Montgomery Avenue between E Main Street and Union Boulevard
Hamlet of Bay Shore and Islip
Start Date: Early January 2023
Posted Date: December 23, 2022
The route will cover approximately 5.62 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Moffitt Boulevard between Grant Avenue and Commack Road
Commack Road between Moffitt Boulevard and Wallace Street
Wallace Street between Commack Road and Winganhauppauge Road
Winganhauppauge Road between Wallace Street and Sunrise Highway South Service Road
Whitman Avenue between Cornell Street and Dartmouth Street
W Pine Street between Whitman Avenue and Fernade Boulevard
Islip Avenue between W Pine Street and Spur Dr S
Spur Dr S between Islip Avenue and Ferndale Boulevard
Sunrise Highway between Whitman Avenue and Brentwood Road
Brentwood Road between Sunrise Highway and Montana Avenue
Brentwood Road between Sunrise Highway and north of Redington Street
Tillie Street turning into E William Street between Brentwood Road and Brook Avenue
Roundabout between E William Street and Sunrise Highway South Service Road
Penataquit Avenue between Catherine Street and Union Boulevard
Union Boulevard between Penataquit Avenue and Chapman Place
Hamlets of West Sayville and Sayville
Start Date: Early January 2023
Posted Date: December 23, 2022
The route will cover approximately .66 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Brook Street between Montauk Highway and Dale Drive
Cherry Avenue between 2nd Street and Easy Street
Easy Street between Cherry Avenue and Roosevelt Avenue
West Islip
Start Date: September 2021
Posted Date: September 2, 2021
The route will cover approximately 1.3 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Sunrise Highway South Service road west of Udall Road
Udall Road between Sunrise Highway South Service Road and Sylvia Drive
Udall Road (turns into Higbie Lane) between Higbie Drive and the intersection at Carnation Road and Paprocki Avenue
LIRR Row Adjacent to Union Boulevard between Higbie Lane and the intersection at Cooper Street and George Street
Brentwood and Deer Park
Start Date: November 2021
Posted Date: November 8, 2021
The route will cover approximately 2.0 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Edgewood Preserve Right Of Way between G Road and Long Island Avenue
Long Island Avenue between Edgewood Preserve Right Of Way and Commack Road
Pine Aire Drive between Orgill Avenue and Dunton Avenue
Hauppauge
Start Date: September 2021
Posted Date: September 17, 2021
The route will cover approximately 0.49 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Blydenburgh Road between Estelle Avenue and Milmay Avenue
Express Drive North (Long Island Expressway) between Veterans Memorial Highway and Blydenburgh Road