Town of North Hempstead
Power On Projects
For a list of completed projects, visit the Town of North Hempstead Completed Projects page.
Village of Westbury
Start Date: Mid-January 2025
Posted Date: 01/02/25
Crews will be working on about .48 miles of the branch line on the following streets:
Drexel Avenue between Ivy Avenue and Grand Street
Ivy Avenue between Drexel Avenue and Maple Avenue
St. Brigids Lane south of Drexel Avenue
Villages of East Williston and Mineola
Start Date: Mid-January
Posted Date: 01/02/25
Crews will be working on about 3.41 miles of the mainline on the following streets:
Sagamore Avenue between Ogden Avenue and East Jericho Turnpike
Windsor Avenue between Sagamore Avenue and Roslyn Road
Roslyn Road between Windsor Avenue and East Washington Avenue
Jericho Turnpike between Andrews Road and Roslyn Road
East Jericho Turnpike between Roslyn Road and Pershing Parkway
Willis Avenue between Hopkins Avenue and Washington Avenue
Mineola Boulevard between Jericho Turnpike and Washington Avenue
Columbus Parkway between East Jericho Turnpike and Raff Avenue
Raff Avenue between Roslyn Road and Donna Lane
Donna Lane between Raff Road and Hill Street
Hill Street between Barwick Boulevard and Donna Lane
Garfield Avenue between Walker Road and just west of Emory Road