Town of North Hempstead

Completed Projects

The following projects have all been completed.

Hamlet of Roslyn Heights and Villages of East Hills and Old Westbury

Start Date: Mid-April 2023
Posted Date: April 10, 2023

The route will cover approximately 5.45 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Powerhouse Road between Colony Lane and Helen Drive
Glen Cove Road between Old Westbury Road and I U Willets Road
I U Willets Road between Hummock Lane and Old Westbury Road
Old Westbury Road between Quaker Lane and South of I U Willets Road
Store Hill Road between Old Westbury Road and Post Road
Old Country Road between Red Ground Road and East of Wheatley Road
Wheatley Road between Old Westbury Road and Trusdale Court


Hamlet of Port Washington

Start date: Mid-April 2022
Posted date: April 5, 2022

Crews will be working on about 1.86 miles of the mainline on the following streets:
Port Washington Boulevard (NY 101) between Sandy Hollow Road and Main Street
Delaware Avenue between N Maryland Avenue and Port Washington Boulevard (NY 101)
N Maryland Avenue between Delaware Avenue and Ohio Avenue
Port Washington Boulevard (NY 101) between Bernard Street and Concord Road
Vanderventer Avenue between S Bayles Avenue and Port Washington Boulevard (NY 101)
Willowdale Avenue between S Bayles Avenue and Port Washington Boulevard (NY 101)
Beechwood Avenue between S Bayles Avenue and Port Washington Boulevard (NY 101)


Hamlets of Herricks and Searingtown

Start date: January 2022
Posted date: January 4, 2022

The route will cover approximately 1.22 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Shelter Rock Road and Links Drive to north of Searingtown Road and Old Searingtown Road
Oxford Street between Moore Street and Herricks Street
Moore Street between Hillside Avenue and Oxford Street


Hamlet of New Cassel and the Village of Westbury

Start date: Early January 2023
Posted date: December 23, 2022

The route will cover approximately 3.15 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Railroad Avenue between Sherman Street and Hopper Street
Sherman Street between Railroad Avenue and Broadway
Broadway between Grand Street and Grand Boulevard
Siegel Street between Roman Avenue and South of Broadway
Grand Boulevard between Covert Lane and North of Church Street
Union Avenue between Post Avenue and Monitor Street
Powells Lane between Union Avenue and Rockland Street
School Street between Rockland Street and South of Union Avenue
Maple Avenue between Linden Avenue and East of School Street
Rockland Street between Post Avenue and Cambridge Avenue
Post Avenue between Castle Avenue and North of Asbury Avenue East
Asbury Avenue East between Fulton Street and Post Avenue


Village of Port Washington North and Port Washington

Start date: November 2021
Posted date: November 8, 2021

The route will cover approximately 0.45 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Radcliff Avenue and Soundview Drive
Harbor Road between Valley Road and Port Washington Boulevard
Irma Avenue between Mullon Avenue and Main Street


Villages of Garden City, Mineola, and Williston Park and Carle Place

Start date: November 2021
Posted date: November 8, 2021

The route will cover approximately 0.81 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
3rd Street between Willis Avenue and Main Street
Willis Avenue between Front Street and Old Country Road
3rd Street between Willis Avenue and Roslyn Road
Roslyn Road between Front Street and Old Country Road
Old Country Road between Washington Avenue and Spruce Street
Vanderbilt Drive N between Old Country Road and LIRR
Voice Road north of LIRR to substation
Rear property on Pell Terrace between 1 and 9
Rear property on Clinton Road between 264 and 272


Villages of East Hills and Brookville

Start date: July 2020
Posted date: July 29, 2020

The route will cover approximately 3.11 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Northern Boulevard between east of Addison Lane to west of Cedar Swamp Road
Rear property east of Flamingo Road between Northern Boulevard and Tara Drive
Rear property north of Tara Drive and south of Northern Woods Road between Flamingo Road and Peacock Drive
Rear property east of Peacock Drive between Tara Drive and Falcon Road
Rear property north of Falcon Road between Peacock Drive and Hummingbird Drive
Rear Property east of Gold Coast Road between Northern Boulevard and Old Wheatley Road
Private Road (off of Old Wheatley Road and east of Gold Coast Road) between Old Wheatley Road and Meadowbrook Lane